EMERSON—Drivers, take note. Here’s an update on plans for the next 10 days of work being done on Kinderkamack Road spanning from about 100 feet south of Etna Avenue to 30 feet north of Jefferson Avenue, including sections of side streets. Expect delays.
- Monday, Aug. 14: Milling of side streets.
- Tuesday, Aug. 15: Resetting of manhole castings; projected 8 p.m. start: milling of Kinderkamack Road.
- Wednesday, Aug.16: Resetting of manhole castings where necessary; projected 8 p.m. start: paving of Kinderkamack Road.
- Friday, Aug. 18: Paving side streets.
- Monday–Wednesday, Aug. 21–23: Laying down of striping and markings.
This schedule is subject to minor changes.