TOWNSHIP OF WASHINGTON, N.J.—The township administrator told council Nov. 9 that although all investigation work and most future remediation costs will likely be covered by state funding, officials still don’t know what total remediation of the 6.1-acre site will cost or how long the environmental cleanup will take.

Administrator Mark DiCarlo told council Nov. 9 that Boswell Engineering had completed a preliminary site assessment and site investigation report on Swim Club contamination, totaling 3,010 pages, and that it will be submitted to the state Department of Environmental Protection.

However, DiCarlo added, “At this time, we are unable to identify a timeframe or cost for decontamination of the property.” The PCB contamination was first identified more than two years ago following a Boswell pre-demolition report on the swim club property.

Moreover, DiCarlo said the next required documents to be completed include the self-implementation plan and the remedial investigation report. DiCarlo said that both documents were “being worked on” and would be submitted to the U.S. Environmental Protection Agency when completed.

See “PCB contamination found beyond former swim club site,” by Michael Olohan, Sept. 19, 2026, at thepressgroup.net. The township also has a webpage dedicated to the swim club acquisition, future uses and funds spent at twpofwashington.us/page/swim-club-property-plan.

DiCarlo said a grant previously received from the NJDEP Hazardous Discharge Site Remediation Fund will reimburse the township for 100% of the covered investigation costs. He noted that officials were also applying to the same state fund to reimburse up to 75% of the site’s remediation costs. He said the council has also applied to its Joint Insurance Fund to help cover remediation costs.

450 Pascack Road plans

The township engineer, Beckmeyer Engineering of East Rutherford, has submitted a proposal to oversee a design phase and public bidding to improve the township-owned property at 450 Pascack Road, which will include upgrades such as parking and passive recreation options, said the administrator at the Nov. 9 council meeting.

Administrator Mark DiCarlo said the engineer’s proposed work will be paid for fully by a previously received state DCA Local Recreation Improvement Grant. Pascack Press requested a copy of engineer Glenn Beckmeyer’s proposal, which was not attached to the agenda. No timeline for the engineer’s work or upcoming improvements was mentioned.

The prior DCA grant was for $66,000. However, $32,000 was spent on demolition and debris removal of the property’s former home and barn, and $10,000 on asbestos remediation prior to demolition, also funded by the grant.

DiCarlo said at a previous meeting that councilors preferred a parking lot adjoining Memorial Field and passive recreation options such as benches, a picnic area, landscaping, a butterfly garden and a rain garden.

DiCarlo said that grant writer David Biunno of GLD Associates will be submitting a Community Development Block Grant application to make Americans with Disabilities Act (ADA) parking improvements. He said Biunno is also researching a grant for public electric vehicle charging stations at the parking lot if council approves.

Brook restoration ‘nearing completion’

In addition, DiCarlo said that the $700,000-plus Musquapsink Brook project, awarded to Downes Tree Service, is “nearing completion” with bank stabilization repairs near the Washington Avenue bridge. He said before-and-after photos will soon be posted on the township website. He noted that he and Mayor Peter Calamari walked the project area and were impressed by the improvements.

In late March, DiCarlo noted the township received a $600,000 federal grant, secured through Fifth District Congressman Josh Gottheimer’s office, to help fund Musquapsink Brook streambank restoration. More than three years ago, a Boswell brook condition report identified two severely eroded streambanks near sanitary waste manholes, which threatened to pollute the stream and foul water that heads toward Oradell Reservoir, a source of drinking water.

The project was awarded in April to Downes Tree Service to repair streambanks near two sanitary manholes, remove sediment shoals impacting brook flow and stabilize streambanks to prevent future erosion. Downes was the lowest responsible bidder at $669,280. Including an estimated $60,000 for Boswell Engineering’s bidding services and work site inspections, total project costs come to approximately $729,280.